Showing posts with label LeMay Erickson Willcox Architects. Show all posts
Showing posts with label LeMay Erickson Willcox Architects. Show all posts

Wednesday, August 29, 2012


The redevelopment of West End's library and fire station--that long running saga--has hit another speed bump. EastBanc-W.D.C. Partners LLC, the development team, had spoken optimistically about breaking ground in 2012, but it looks like a lawsuit filed by a library watchdog group will push that back until March 2013 at the earliest.

It's been a long road. The development team--which consists of EastBanc, The Warrenton Group, Dantes Partners, and L.S. Caldwell & Associates--was granted the project in 2007, then lost it due to community outcry that there hadn't been a fair bidding process. In 2010, they won a competitive bid, beating out one other competitor, and since then have held some 70-odd meetings (by their own count) to keep the community abreast of plans. 

The project has always been a complicated one. It includes two separate parcels: one, Square 37, sits at the corner of 24th and L streets and includes the low-rise, funky West End Library, as well as a police operations facility and a parking lot; the other is Square 50 at 2225 M Street and and includes the West End fire station. EastBanc won the project by promising to rebuild the library and fire station; in return, the city gave the developers the land, then valued at $20 million, for free.

And therein lies the problem. The DC Library Renaissance Project, an organization founded by Ralph Nader to improve the city's library system, claims that EastBanc is dodging the affordable housing requirements that exist under the city's newish inclusionary zoning policy by calling the library and firehouse "amenities."

"We don't understand why [the library and firehouse] would count on the balance sheet of the PUD process for the developer," explained Robin Diener, director of the DC Library Renaissance Project. "The city is selling the land to EastBanc. They're not giving money, they're giving new facilities as payment." As a result, says Diener, the developers should still provide a certain percentage of affordable housing in each square as required under inclusionary zoning.

But the DC Zoning Commission agrees with EastBanc. This spring, the commission granted the developer's application for a map amendment for Square 37. And in June, when the DC Library Renaissance Project applied for a reconsideration of that decision, the Zoning Commission denied their effort, writing, "The enhanced level of service that will result from the construction of the new library and fire station so clearly will enhance the neighborhood that they set a benchmark in excellence for any future requests for Inclusionary Zoning waivers through the PUD process."

In response, the library advocates filed a notice last week in the DC Court of Appeals that they intend to appeal the Zoning Commission's decision, not an idle threat since the group has been at least partially successful in stopping the project since at least 2006.

"We're certain there's no merit, but we'll file a brief arguing that no, the Zoning Commission didn't make mistakes in its decision," said Joe Sternlieb, EastBanc's vice president for real estate acquisitions, in response to questions about the suit. "It can take up to a year, and can cost developers up to $1 million to defend. It's really a nuisance suit."  When will the issue be resolved? "The courts will decide," said Sternlieb. "Hopefully before March."

Despite the threat hanging over its head, EastBanc is moving forward. Sternlieb said that the Square 37 project has gathered all the necessary approvals, including from the Commission on Fine Arts, and the firehouse is almost there. The company is currently working out construction documents and getting financing in place, and Sternlieb is hopeful that they could still break ground in March 2013.

The project, which is being designed by TEN Arquitectos, WDG Architecture and Lemay Erickson Willcox Architects, hasn't changed substantially since 2010 (though TEN hasn't bothered to add the project to its website). Square 37 will become a 10-story building with a library and roughly 7,000 square feet of ground floor retail that faces 23rd Street--including a coffee shop on the corner, adjacent to the library--plus 164 market rate units above. That section does not include any affordable housing.




But the fire station portion does; in fact, all 61 rental units will be priced at 60 percent of the area median income. Some of those units are created under the inclusionary zoning policy, but EastBanc said it couldn't afford to make the entire building affordable without assistance, and so the District kicked in an extra $7 million to go the final distance.

Robin Diener and her colleagues aren't happy about that. Given that the two sites comprise some of the most valuable land in the District, they believe the initial development deal should have been structured so that the city made, rather than spent, money on it.

But neighborhood groups, including the West End Library Friends, Foggy Bottom Association, and the ANC covering the region, overwhelming support the project. 



Washington D.C. real estate development news

Monday, November 15, 2010

By Beth Herman


In prehistoric times,it was a means to keep warm and char that woolly mammoth (please pass the salt), and in the 2000 film “Cast Away,” Tom Hanks unabashedly called himself a god on the night he created it. But in the dense, exploding, urban atmosphere of today, a roaring fire isn’t the answer.

For Reston, Va.-based LeMay Erickson Willcox Architects, purveyors of safety design and creators of more than 50 fire and rescue facilities over three decades, the structures they build in response to the demand for fire and rescue services in expanding metropolitan areas are the real answers, and maybe in more ways than one.

The Spark

Back in 2006, when the City of Alexandria sought a redevelopment plan to revitalize Potomac Yard, a former rail yard sited in the city’s north end which for more than 100 years served as the area’s primary freight yard and extended all the way into Arlington County, the idea of mixing rescue with residents was completely unprecedented according to firm principal Paul Erickson.

“We’re not aware of any other building in the U.S. that combines an apartment structure with a fire station,” Erickson said of the prototype mixed-use design for The Station at Potomac Yard No. 9. “We believe there are one or two overseas: one in London and there might be one in South Africa, but we’re not aware of any here.”

Very much a collaborative effort where the collegiality on the project was “infectious,” Erickson was quick to emphasize, the 170,000 s.f. structure, which includes two below grade parking floors and was earmarked as both low-income and affordable housing, is the painstaking result of the efforts of legions of civil engineers, traffic consultants, historic and design review entities, fire and housing office officials, sound consultants, sustainability inspectors, a “forward thinking” general contractor–Whiting-Turner Contracting Company–and two architecture firms. “It was the best team spirit of any project I’ve been involved in since the beginning,” Erickson affirmed. “One of the distinguishing characteristics of this one was everybody sort of catching a vision of something that was unique and had never been done.” What’s more, because the City was exploring how best to manage a master redevelopment plan for the area, it wanted to make sure that if things were built, they could be protected, Erickson said, referencing the 22,500 s.f. fire station component.

Vibrations Under Fire

According to LeMay Erickson Willcox senior associate Lynn Reda, director of the firm’s public safety studio, most of the projected noise concerns had more to do with the operation of the fire station and the vibration between it and the 64 residential units above than the fear of whining sirens. “They’re not supposed to turn their sirens on until they are off the property,” Reda said, adding they are naturally traveling away from the building. To that end, acoustic technology experts Polysonics Corporation was retained, resulting in the design of a special sound-abating slab between the fire station’s ceiling and the residences above. “We were certainly concerned about vibration,” Reda said, noting that the parking garage and fire station consist largely of poured concrete while the units above are wood frame structures: the change in materials mitigating sound. Because of the station’s four pendulous 14x14-ft. bay apparatus doors (plus one more for HAZMAT trailers) that open and close several times in a 24-hour period, instead of traditional overhead doors with ceiling-mount motors that would impact the units above, the architects used “side-parting” doors. Additionally, the 1,2 and 3-bedroom residences above are arranged in a U-shape around the apparatus bays, which further attenuates sound from beneath.

Fire Walls (and roofs and floors)

Where sustainability is concerned, two different green ratings systems were applied, one to the fire station to achieve LEED Silver, with the residences submitting to EarthCraft certification. According to Reda and Erickson, EarthCraft, which is residential in nature, dispatches inspectors during construction to examine the thermal envelope and is more focused on energy conservation including appliances, for example, that have Energy Star ratings. For the building’s LEED credentials, Reda said 100 percent of the parking is below grade, considered exemplary performance from the heat island effect. The sloped red metal roof has a high SRI (solar reflective index), as does a concealed mechanical well behind it. Arriscraft block– visible at the base of the building and which provides the appearance of a heavily-rusticated stone base but is essentially veneer–is regional. Cement block, which comprises the station’s interior walls, has an inherent recycled content and wood used in doors and cabinetry is FSC (Forest Stewardship Council)-certified. Occupancy sensors for lighting and occupant-controlled thermal elements are present, as is radiant heat in the floors of 15 bunk rooms. “One of the reasons we did that is because they are located above the cold, two-level parking garage and sleeping rooms need to be warm in winter,” Reda affirmed. A small municipal park sited in front along with perimeter plantings, irrigated by rainwater from garage-based cisterns that collect roof water, qualifies for green space.

Where There’s Smoke

For Erickson, whose grandfather was a firefighter (though he never knew him) in St. Paul, Minnesota, and for Reda, whose reputation for “living the job” comes from her constant immersion in firefighter training exercises and overnights at stations on out of town projects, fire and rescue station work is proverbially in their blood.

“I’ve cut open roofs, extinguished car fires, done search and rescue through smoke-filled houses,” Reda said (much in the way an actor may research a role). Because firefighters have their own culture, and characteristics of their culture may vary significantly from city to city, state to state, region to region, Erickson and Reda said it is important to understand how one city for which they are designing a facility might do things as opposed to people and factors that influenced the last project. “It’s important to be able to ask the questions that will help you design that building and not change them (the firefighters) culturally into something they don’t want to be,” Reda said.

Additionally, safety facility design has metamorphosed from the smaller, sparse, utilitarian structures of 20 and 30 years ago into the framework that needs to support escalating urban areas, as well as a changing firefighter demographic. “Back in 1979, there really weren’t any women in fire and rescue emergency services and that’s changed a lot,” Erickson reflected. “At Potomac Yard, you’ll see gender-neutral spaces that include private bunk rooms with individual restrooms consisting of a lavatory, shower and water closet.” According to Erickson, this allows for flexibility of shift and demographics. “It’s a pretty elegant solution to staffing and gender issues,” he said. With fitness paramount to employee health and morale, the architects said relatively sophisticated gym spaces with high enough ceilings to accommodate state-of-the-art equipment are encouraged in their designs, and not simply the dumb bells-in-the-basement stock of older stations.

“And from a firefighting perspective, equipment such as ambulances, engine and ladder trucks – they’ve gotten bigger and bigger and bigger,” Reda said, noting sometimes the older facilities cannot be retrofitted to accommodate them and stations must be built larger. What’s more, she cited a greater understanding of the impact of firefighting on gear itself (it costs $1,000 to suit-up a professional), and the trend in building climate-and light-controlled storage rooms to manage gear’s off-gas toxins following a fire.

On Fire Now!

Alluding to the firm’s website, Erickson said despite so many requirements there is no uniform design response for fire stations. “You’ll see some very contemporary designs, as well as those that try to take on historic characteristics and blend into an historic neighborhood,” he explained, noting that because of Rust Orling Architecture’s (the second firm involved) high standing for work within an historical context in Alexandria, fulfilling the requisites of the design review board, planning commission, town council and neighbors to develop the character of the building’s exterior was supremely achieved. The result, Erickson said, is a “Richardsonian-Romanesque kind of architecture, but done in a Virginia brick that blends the image of a civic building with the particulars of Old Town Alexandria.” In fact, among the multitude of awards the building has received is a 2007 U.S. Council of Mayors’ Award and a 2010 Craftsmanship Award.

With a project in Durham, New Hampshire and two projects in development in the District that will apply similar mixed-use principals, one where an 1895 horse-drawn pumper on Georgia Avenue will yield to affordable housing and improved emergency response with one proverbial stroke, Erickson indicated word is getting around. And with creativity extending to financing, in Alexandria some of the cost of the $23 million project was defrayed by funding sources and options that included the developer, Potomac Yard Development, contributing just over $14 million for both the fire station and residential components, plus donating the land, and by using Virginia Development Housing Authority (VDHA) tax credits.

“I think what this all really demonstrates is that you can think outside of the box,” Erickson said.